The refresh action should be used periodically to update data in the plan to reflect the current base data. Changes made in the base data layer are not automatically pushed in the plan layer. The plan layer is a snapshot of the base data layer at the time the project was initially created. The refresh process cannot be completed before the conflicts are resolved.

 

CM-CHA~1_img60

 

User can refresh the project workspace by clicking Project -> Refresh from Base CM-CHA~1_img61

 

Refresh Options

Refresh dialog box gives use the following options before Run. clicking Project -> Refresh from Base->Run

Function

Option

Description/Use

Conflicts

Either option

Resolve auto: Version

Resolve auto: Parent

When there is a conflict update the project data with parent base data or keep the project data

Automatically repair problems

Select check box

Make names unique by adding numbers

Situations where unique names are required resolve issue by adding sequential number at the end of the name

Information

Select check box

Show conflict

Write to protocol windows

Show changes

Show conflict after analysis

Write details to ConnectMaster protocol windows

Show changes made